To determine where our corners would be we needed to take into account all of the restrictions and conditions present. Knowing that we want to stay under 200 square feet we selected the site and upon analysis we decided the site condition really only allowed somewhere near 200 sqft. With that in mind we took to configuring out plan, a rectangle is the most efficient shape for a work space.
Step 1- Draw it out!
Pier Detail |
Pier footing form |
Step 3- Mix and pour your concrete,
Poured concrete footer |
Stone pile |
Step 5- Watch the Laying a Fieldstone Pier video
Fieldstone pier |
And there you have it! The cast concrete capstone was also made on site. The final step here will be to screw a temporary skirt board on the framing to create a form to pack high strength grout between the capstone and the framing on the inside corner. Notice the "Floating Column" making a cameo appearance! More on that later! Cheers.